2022 Improvement Projects

Projects completed by the building and grounds (B&G), board members, or an outside-hired contractor are listed in normal text. Projects completed by other volunteers are highlighted in green text. Please let us know if we’ve missed anyone or if a completed project.

Lobby Renovation

What started as a casual conversation and suggestion in 2021 turned into a full-on renovation in the spring of 2022. A majority of the materials and all of the labor for this project were donated by the B&G committee.

  • The walls were patched, prepped, and painted with a new, simplified color scheme.
  • The baseboards and floor were cleaned to remove grime and old paint.
  • The surface-mounted ceiling light fixtures were removed. New, high-lumen bright-white LED recessed lights were installed. Track lighting was installed at two locations to highlight bulletin boards and plaques.
  • New receptacles were installed in the ceiling at the lobby’s north end to power a digital signage monitor.
  • New signs were installed for the restrooms and staff-only areas.
  • Door closers were re-painted with silver/metallic paint to improve appearance (note that in the coming years, replacement of all doors is proposed).

Thanks to a generous donation by Christina Randall, we were able to:

  • Custom build a new wooden butcher block manager’s desk with motorized height adjustment (this replaced an old, worn-out “teacher desk” that was beyond the point of refurbishment).
  • Purchase a new modern-style lateral file cabinet (to replace several smaller, old file cabinets).

Sagging Ceiling, View #2

Image 23 of 23

Another view of the sagging ceiling prior to repair. Photo taken on March 9th, 2022.

Grounds Improvements

A good friend of B&G, David Dodge, with his crew’s help:

We also need to thank the Aiken, Bernath, Chipman, Curd, Henderson, Katcherian, Niemi, and Peters families for their tremendous contributions during our spring clean-up. Please let us know if you volunteered during the 2022 spring clean-up and we missed your name.

Our staff also chipped in pre-season by painting various items, including the volleyball/tetherball poles, power washing, and pulling weeds.

Snack Shack Air Conditioner

Details to follow.

Network and Camera Upgrades

In February, a solar-powered “dumpster cam” was designed and installed to monitor the north end of the parking lot in response to dumping by outside individuals.

The Arlo camera system (installed in 2019) was decommissioned. While fundamentally a solid system, it lacked flexibility as it was bound to the wireless range of the base station located in the clubhouse. Furthermore, cameras required frequent recharging. While there were options to eliminate the charging issue, we desired coverage for the full property.

The camera system was replaced with wired 5 MP (megapixel) turret-style cameras. We intend to expand this system in the coming years as the budget allows. As of 2022, we have multiple cameras monitoring the property 24/7.

Internet and Phone Upgrades

We now use a dedicated VoIP phone provider – separate from our cable internet provider. This was done to reduce costs and to bring additional flexibility. We can now change internet providers (i.e., Spectrum, WOW!) without swapping equipment and/or porting our phone number. It also allows us to maintain phone service without an internet provider. This way, internet service could be fully canceled during the off-season to save money.

We changed internet providers to take advantage of the promotional rates and determined we should own our cable modem to avoid the monthly equipment rental fee. A modem was generously donated by a club neighbor, Gordon Hastie.

Three VoIP handsets were installed in the club (you may have noticed them in the lobby, with the club logo on their screens). We also added a phone in the pump house.

Other Projects: Club House

Other Projects: IT

Getting the new network switch up and running was actually quite an involved project. To save money, we purchased a used “for parts only” on eBay, understanding that repairs to its power supply would be necessary.

The switch arrived in a non-functional state (though with a like-new appearance). It would partially power up, but it wasn’t functional. This model has a known reliability issue (widely complained about in support forums). Fortunately, a fix was (supposedly) quite easy.

Weeks later, after a couple of rounds of component replacement – the switch sort of worked. Unfortunately, it would still power itself off after a few days of use.

So, we purchased a second “for parts only” unit. This one appeared to have a functional power supply but wouldn’t boot up properly. At this point, the total investment was still well below the cost of a new switch, but patience was waning.

Fortunately, a fully-working switch was born with the power supply from the second unit and the mainboard from the first unit. We combined the other parts, and the double-defective unit was re-sold (clearly sold as non-functional).

Months later, the switch has been operating flawlessly. Ultimately, the unit was donated to the club by B&G.

Other Projects: Pool Deck

Other Projects: Pump House

Chlorinator

No, this isn’t a repeat from 2021. The chlorinator required continued attention in 2022.